Current Sprint Cycle: 122
Build Start Date: 1/22/2025
Build End Date: 2/4/2025
Testing Start Date: 2/7/2025
Testing End Date Testing: 2/18/2025 (HOLIDAY?)
Key Focus Areas: This is the last full PI 18 sprint.
Continuing the build on Activity Menu Stepper for Customer Portal
Continue updating aspects of MiEHDWIS for more ADA compliance
Work on the integration of PayPlace (CEPAS) for online payment
Adding Contributors card on the external User Activity Details and Customer portal
Bug Fixes
Upcoming Sprint Cycle: Bug Bash Release 18 -Round one
What is a bug bash? A bug bash is a dedicated sprint cycle to fixing and addressing all the reported bugs during development of a new future release.Build Start Date: 2/5/2025
Build End Date: 2/18/2025 (HOLIDAY?)
Testing Start Date: 2/21/2025
Testing End Date Testing: 3/4/2025
Upcoming Sprint Cycle: 124 - Bug Bash Release 18 - Round two
Part 2 of the Release 18 bug bash.Build Start Date: 2/19/2025
Build End Date: 3/4/2025
Testing Start Date: 3/6/2025
Testing End Date Testing: 3/18/2025
...