Back on the Global File Upload screen, finish filling out the required fields by entering the Entity information for each file.
Click Next.
You’ll be prompted to review the files you uploaded; you can click the Back button to make revisions if needed.
The Pick the Activity Type, Monitoring Schedule, should be prefilled.
Click Upload.
A new screen will appear, displaying all the documents you just uploaded.
Keep note of the Bulk Upload ID at the top of the table, in case you want to do a document search for the list.
The workflow is configured to transition the ‘Draft’ Monitoring Schedule Activities to ‘Active’ overnight. However, you can still manually transition activities if you choose too. Upon transitioning the activity to Active, a notification will be sent to the water supply.
The Monitoring Schedule Activities are externally visible. External Users can locate and download copies any Monitoring Schedule files that are marked externally visible.
...