Click on the Begin Inspection button to use the integrated inspection form and submit data directly to EGLE. EGLE’s inspection questions have been updated and are now part of MiEHDWIS.
Review the information under Description, on the right-hand side of screen.
When ready, navigate to Tasks and select Start Form.
This will bring you to a new form entitled Campground Inspection form. The Inspection Due date Date will be listed, as well as the Inspection ID and the Inspection Type of Inspection.
Please confirm that your Inspection type is correct.
Complete the Inspection Reporting Method.
Upload an Inspection Report - If this route is selected, you will need to upload a scanned paper or digital inspection form after completing the form and supplying your recommendation of compliance Status.
More information regarding this process will be listed in step 10.
Complete Inspection Questions Below- This route has all the required questions listed in the form, with your recommendation of compliance Status.
Report a Corrective Action - This route is selected to report the results of a follow-up inspection.
Select Licenses Status - Confirm with the campground representative you are with, while completing your inspection.
...
Complete the remaining questions in the inspection form. Be sure to set
Set the Inspection Status/Resolution and select Complete.
✔️ In Compliance - No issues or concerns were identified, no compliance comments were included on the report, and no EGLE staff review is required.
✔️ In Substantial Compliance - Only minor issues or concerns were identified, compliance comments are included on the report, and EGLE staff will review.
A follow-up inspection may be necessary.
❌ Not In Compliance - Multiple minor issues or concerns, or one or more major issue or concern was identified, compliance comments are included on the report, and EGLE staff will review.
A follow-up inspection is required.
Continued licensure and operation are not recommended.
If you selected Upload an Inspection Report in the Inspection Form on step 6, a new task will appear.
You will need to Upload the Inspection Report in the Inspection.
Scroll down to the Customer Attachments card.
Click on the Upload Attachments button.
Browse or drag the attachments to the upload modal.
Select Inspection Report from the File Type drop-down list and click the Save button.
Scroll back up to the Tasks card and click on the task box to check the task as complete.
...
If you selected Complete Inspection Questions Below in the Inspection Form on Step 6, you have the option to upload additional supporting documents.
If you have additional supporting documents.
Scroll down to the Customer Attachments card.
Click on the Upload Attachments button.
Browse or drag the attachments to the upload modal.
Select the type of file from the File Type drop-down list and click the Save button.
If changes are needed on the form, select Edit Form.
When Inspection in completed select Submit to EGLE.
...
For In Compliance inspections, the current Status of the activity will change to Approved. EGLE staff will be notified of its receipt. No changes can be made to the activity. If you need to submit changes, contact EGLE staff by email. |
---|
For In Substantial Compliance and Not in Compliance inspections submitted, the current Status of the activity will change to In Review. EGLE staff will be notified of its receipt. No changes can be made to the activity. If you need to submit changes, contact EGLE staff from the Messages card of the activity. Scroll down the activity to locate the Messages card. How do I send a message to EGLE staff? |
---|
Option 2 - Seasonal Closure
Click Seasonal Closure for an end of season closure.
Please note, if you selected Seasonal Closure on accident, please reach out either the Campground program staff at EGLE-DWEHD-CampgroundProgram@Michigan.gov or the MiEHDWIS Help Desk. Be sure to include the activity number (ACT-XXXXXX).
This will change the status of the activity to Closed/Seasonal and close the activity.
...
Click Permanent Closure to signify the permanent closure of a campground.
Please note, if you selected Permanent Closure on accident, please reach out either the Campground program staff at EGLE-DWEHD-CampgroundProgram@Michigan.gov or the MiEHDWIS Help Desk. Be sure to include the activity number (ACT-XXXXXX).
This will change the status of the activity to Closed/Permanent and close the activity.
...